Chips can be ordered and buildings can be built. Grid connections take years. That is why the most valuable thing a data centre developer can own in 2026 is a confirmed megawatt of power, and why acquirers are paying for it. AI data centre demand is growing faster than electricity grids can connect it. The scarce asset is no longer land or buildings. It is confirmed power. The AIP, MGX and BlackRock GIP consortium closed its $40bn acquisition of Aligned Data Centers on 21 July 2026 and committed another $5bn of growth capital. In Texas, data centres account for around 90% of potential demand in ERCOT’s large-load queue, and developers now pay $50,000 per megawatt and must prove land control before studies start.

Research · Digital infrastructure

Buying the Grid: Why Power Access, Liquid Cooling and Substation Proximity Now Set the Price in Data Centre M&A

Chips can be ordered and buildings can be built. Grid connections take years. That is why the most valuable thing a data centre developer can own in 2026 is a confirmed megawatt of power, and why acquirers are paying for it.

Joash BoytonFounder & Managing Director

Independent analysis and opinion. How we research

Published
Reading time
7 min read
Aligned Data Centers sale to AIP, MGX and GIP, closed July 2026
$40bn
Extra growth capital committed to Aligned at close
$5bn
Share of ERCOT large-load demand requests from data centres
~90%
Texas fee developers now pay before grid studies begin
$50k/MW
Aerial view at dusk of a high-voltage substation beside a hyperscale data centre campus

Summary

Summary

  • AI data centre demand is growing faster than electricity grids can connect it. The scarce asset is no longer land or buildings. It is confirmed power.
  • The AIP, MGX and BlackRock GIP consortium closed its $40bn acquisition of Aligned Data Centers on 21 July 2026 and committed another $5bn of growth capital.
  • In Texas, data centres account for around 90% of potential demand in ERCOT’s large-load queue, and developers now pay $50,000 per megawatt and must prove land control before studies start.
  • For acquirers, energised capacity, interconnection agreements, on-site generation and liquid-cooling readiness are now the core valuation drivers.

01 · Research

The constraint has moved to the grid

Power is now the long pole.

A modern AI training or inference campus can need hundreds of megawatts. Chips, servers and even buildings can be procured on timelines measured in months. A new high-voltage grid connection is measured in years: studies, upgrades, permits and construction.

Texas shows the pressure clearly. ERCOT (opens in a new tab) has received hundreds of requests for large-scale connections, and data centres account for around 90% of the potential demand. Regulators now require developers to pay $50,000 per megawatt and prove they control the land before grid studies even begin, a filter designed to clear speculative requests.

02 · Research

Follow the capital

Platform-scale money for power-secured platforms.

The AI Infrastructure Partnership, MGX and BlackRock’s Global Infrastructure Partners closed their $40bn acquisition of Aligned Data Centers on 21 July 2026, and committed a further $5bn of growth capital to expand Aligned’s AI-ready capacity. The size of the cheque reflects a platform with secured power and a pipeline of buildable sites, not just existing halls.

Brookfield has committed more than $25bn to data centre and power infrastructure, pairing capacity with generation. The pattern across the largest investors is the same: own the power alongside the building.

AssetWhy it mattersTime it saves
Energised capacityRevenue can start as soon as tenants fit outYears of grid upgrades
Signed interconnection agreementContracted right to future capacityStudy and queue time
On-site or adjacent generationReduces reliance on grid upgradesTransmission build-out
Liquid-cooling readinessSupports dense AI racks without retrofitMechanical redesign
Local approvals and water rightsLowers permitting and community riskPlanning cycles
What a power-secured platform offers a buyer

03 · Research

Social licence is now part of the asset

Approval risk is priced in.

Regulators are adding expectations as well as fees. In March 2026 the Australian Government released expectations for data centre developers covering national interest, support for the energy transition and sustainable water use, framed explicitly as conditions for maintaining a social licence to operate.

For acquirers this turns community relations, water strategy and renewable sourcing into diligence items with real value attached. A site with approvals, local support and a credible energy plan is worth more than a cheaper site that still has to win them.

04 · Research

What it means for buyers and sellers

Power-first valuation.

  • Value the megawatt, not the square metreBuyers increasingly benchmark platforms on energised and contracted MW, and on the certainty and timing of future capacity.
  • Bolt-ons with power are prime targetsSmaller developers holding pre-approved grid access or generation rights are natural add-ons for the large platforms. Clear documentation of interconnection status is the single biggest value lever.
  • The stack extends to softwareEnergy management, cooling control and capacity-planning software sit in the same buying pattern, as Schneider’s purchase of Shelly showed in September 2026.

Read alongside Inside the Agentic Stack: the software layers agents run on, and the power those layers consume, are both being bought by platforms with long-term capital.

Reference

Frequently asked questions

Why is power access so valuable in data centre M&A?

Because it is the slowest input to secure. Buildings and equipment can be procured in months, but a new grid connection can take years of studies, upgrades and approvals. A developer that already holds confirmed capacity can deliver revenue far sooner, and buyers pay for that time advantage.

What was the largest data centre acquisition of 2026?

The $40bn acquisition of Aligned Data Centers by the AI Infrastructure Partnership, MGX and BlackRock’s Global Infrastructure Partners, which closed on 21 July 2026 with a further $5bn committed for growth.

What is ERCOT’s large-load queue?

The list of requests to connect very large electricity users to the Texas grid. Data centres account for around 90% of the potential demand in it, and Texas regulators now require a $50,000 per megawatt payment and proof of land acquisition before grid studies begin.

What do buyers check in a data centre target?

Energised megawatts, signed interconnection agreements and their timelines, on-site or adjacent generation, cooling capability for high-density AI racks, water rights and local approvals, and the credit quality of contracted tenants.

About the analyst

Joash Boyton

Joash Boyton

Founder and Managing Director, Acquiry · Melbourne, Australia · Global coverage

Joash Boyton is the Founder and Managing Director of Acquiry, a specialist M&A advisory firm focused on the acquisition and sale of businesses. He executes buy-side and sell-side mandates from USD $1M to $500M across technology, SaaS, fintech, payments, gaming, blockchain and emerging verticals, and is not limited to them. Any sector, any market.